update rqm project area with a new project template
One answer
The project area template is used to initialize new project areas with the settings from that template. If you want to change existing project areas, you must use the project area editor.
Comments
Thank you Paul. The reason I asked this question that for rtc, you can make project areas share a process template. When you modify the process template, all the sharing project areas get the changes. For rrc, you can update a project area by importing a changed project template. Both features give you a way of providing consistency. I guess rqm doesn't have something like that?
Correct, RQM is different from RRC/RTC in that once a project area is created from the template it is independent of any modification to the template.