Top Work Item complexity based on Estimation field
Hi all,
I know that use time Estimation (hours format) as a way to establish the complexity of a work item in the backlog may not be a good agile practice, but: Is there another limitation to not have the Estimation field as a possibility for complexity?? In our case the natural way to estimate the complexity of high level tasks is using a estimation based on hours of work. Is possible to use time estimation on RTC to manage these high level work items?? Thanks! Andrs |
One answer
jaguerrero wrote:
Hi all, Using estimates is currently not possible because we consider only integer and enumeration attribute types and estimates are stored as duration. As a workaround you can add a custom attribute of type integer to estimate high-level tasks and use that attribute as complexity attribute. -- Cheers, Johannes Agile Planning Team |