Add a task from a different project in current project


Becky Kohl (345) | asked Jun 09 '14, 3:09 p.m.

User is a member of two projects.

Tasks assigned to user in project 1 apply to project 2 as well.

How can I "import" the task from project 1 to show in project 2's work breakdown? When I click on "Add Work Item", -> "Add Existing Work Item", it would seem that if I could select the other project from the Project Area box, that would work, however the Project Areas box only shows the current Project and does not allow me to select.  Do I need to create a cross-project dependency somehow?

Accepted answer


permanent link
Lily Wang (4.9k714) | answered Jun 09 '14, 7:28 p.m.
 To add a work item of another project area to the plan view, you need to create a cross-project plan. Please see https://jazz.net/library/article/1152 for the details about cross-project plan.
Becky Kohl selected this answer as the correct answer

Your answer


Register or to post your answer.