Plan - Unable to load all children
I'm trying to create a plan in RTC and I'm stuck in the below scenario -
I have a Epic, under which child enhancements and tasks at the last level. The Epic belonging to team area A is planned for say Oct 2014 but the tasks under the enhancements are planned for Sept 2014 or Dec 2014. When I create a plan for "Team Area A" and iteration for Oct 2014 and plan type is "Release Plan" with "Always load all execution items" . I need my plan to load all the tasks as well but I'm unable to view them. I am aware that if I create a plan with the top level iteration (Eg: 2014), I can see all the tasks but that loads a lot of work items and is very slow.
Is there any solution for this?
Is there any solution for this?
Comments
Dinesh Kumar B
JAZZ DEVELOPER Jun 05 '14, 5:50 a.m.