Is there a process to revert a task work flow back to a previous state?


Daniel Ruebush (9715987) | asked May 27 '14, 4:51 p.m.
 I have modified the task and work item work flow and the state groups. Now I am seeing that it is no longer operating as it did. Is there a process to revert it back?

Will I lose data if someone submits work items since?

One answer



permanent link
Donald Nong (14.5k614) | answered May 27 '14, 9:33 p.m.
edited May 27 '14, 9:34 p.m.
If you are asking how to get back to a previous version of the process configuration, consider the process configuration history function.