Can we automate % completion in WorkPacket?
Hi All
Currently, we are updating the work packets manually and these are updated with a % complete based on the progress of children tasks. Can we automate % completion in Work Packet on hours complete in the children tasks compared against the estimate? Can we automate work packet completion figure? |
Accepted answer
Ralph Schoon (63.5k●3●36●46)
| answered Dec 19 '14, 8:48 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
There is some roll-up of child information available in plans. The "Package" work item type needs to be checked (as plan item) in the Process Configuration>Project Configuration>Configuration Data>Planning>Work Item Type Categorization for this to work.
If you need attributes on the work item however, this provides a possible approach: https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/ It is an extension/follow up action as Sam suggests. Abhinav Mishra selected this answer as the correct answer
|
One other answer
nothing provided with the product. Mostly because it is assumed the estimate is not completely correct..
one could write an extension that tried to implement this behavior |
Your answer