Can we automate % completion in WorkPacket?


Abhinav Mishra (1443139) | asked May 16 '14, 6:05 a.m.
edited Dec 19 '14, 4:48 a.m.
Hi All

Currently, we are updating the work packets manually and these are updated with a % complete based on the progress of children tasks.

Can we automate % completion in Work Packet on hours complete in the children tasks compared against the estimate?  Can we automate work packet completion figure?

Accepted answer


permanent link
Ralph Schoon (63.5k33646) | answered Dec 19 '14, 8:48 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
There is some roll-up of child information available in plans. The "Package" work item type needs to be checked (as plan item) in the Process Configuration>Project Configuration>Configuration Data>Planning>Work Item Type Categorization for this to work.

If you need attributes on the work item however, this provides a possible approach: https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/

It is an extension/follow up action as Sam suggests.
Abhinav Mishra selected this answer as the correct answer

Comments
Abhinav Mishra commented Dec 20 '14, 2:20 a.m.

Thanks Ralph

One other answer



permanent link
sam detweiler (12.5k6195201) | answered Dec 19 '14, 7:31 a.m.
nothing provided with the product. Mostly because it is assumed the estimate is not completely correct..
one could write an extension that tried to implement this behavior

Comments
Abhinav Mishra commented Dec 20 '14, 2:19 a.m.

Thanks Sam