Hello,
I use RTC 4.0.3 and I would to modify the resolution date of one workitem.
In fact, I have forgotten to change the state of my workitem last month and now all my custom workload calculates are wrong ...
So, the only solution is to change the resolution date.
Thanks for your help
Regards
Mathieu

0 votes


Accepted answer

Permanent link
 Hello,
I would:
- make the resolution date modifiable (not read-only)
- CSV export my work items with the resolution date exported
- modify the resolution dates in the CSV file
- re-import the CSV file / modify existing work items
make the resolution date read-only

(not tested)

Hope it helps,
Eric
Mathieu Defianas selected this answer as the correct answer

1 vote

Comments

Thanks for this information !!!! It works !!!!

 Glad I could help, Mathieu.

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,029
× 369

Question asked: May 12 '14, 10:25 a.m.

Question was seen: 5,759 times

Last updated: May 12 '14, 1:58 p.m.

Confirmation Cancel Confirm