Mathieu Defianas (15952938) | asked May 12 '14, 10:25 a.m.
Hello,
I use RTC 4.0.3 and I would to modify the resolution date of one workitem.
In fact, I have forgotten to change the state of my workitem last month and now all my custom workload calculates are wrong ...
So, the only solution is to change the resolution date.
Thanks for your help
Regards
Mathieu

Accepted answer


permanent link
Eric Jodet (6.3k5111120) | answered May 12 '14, 10:58 a.m.
JAZZ DEVELOPER
 Hello,
I would:
- make the resolution date modifiable (not read-only)
- CSV export my work items with the resolution date exported
- modify the resolution dates in the CSV file
- re-import the CSV file / modify existing work items
make the resolution date read-only

(not tested)

Hope it helps,
Eric
Mathieu Defianas selected this answer as the correct answer

Comments
Mathieu Defianas commented May 12 '14, 11:42 a.m. | edited May 12 '14, 11:42 a.m.

Thanks for this information !!!! It works !!!!


Eric Jodet commented May 12 '14, 1:58 p.m.
JAZZ DEVELOPER

 Glad I could help, Mathieu.