EWM Code Review Approvals - stay Pending
We have recently started to use Code Review in EWM 7.0.2.
I would very much appreciate any tips regarding this.
Thanks |
Accepted answer
David Lafreniere (4.8k●7)
| answered Feb 18 '22, 12:03 p.m.
FORUM MODERATOR / JAZZ DEVELOPER edited Feb 18 '22, 12:06 p.m. I'm going to provide an answer which is similar to the comment Vinitha provided, so that this question can be marked as answered.
You also asked about having the ability to 'close' a code review. This is not required. If you close a code review, it essentially locks down the work item, which prevents you from adding additional change sets on the work item (eg: to avoid delivering a change and attaching it to the work item after things are approved). Certain customers may need these tighter constraints, but in general if you are comfortable with the old workflow of trusting the devs, and relying on email notifications, or seeing incoming changes delivered by other people then it's not required to close the code review. Ralph Schoon selected this answer as the correct answer
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Thank you Vinitha!
You are absolutely right.
Obviously, the RTC6 Client is not fully compatible with EWM7 server.
We have problems using the version 7.0.2 Client and are still using the RTC6 Client.
Managing large number of modules is very difficult using v7.0.2 Client because of the changed filtering options:
Component additions/removals not considered when "show unchanged components" is deactivated (469629)
Unfortunately, the above feature was not implemented as proposed :(