RTC Constraint Date Type is making date attribute Read Only

 For a date attribute in RTC, the requirement is to put only date hence i changed the display type to constraint, but in  UI I see the field as read only with none option. Is it right behaviour?

1 vote



One answer

Permanent link
The "Constraint Date" is normally used in Formal Project Management process configuration combined with "Constraint Type". "Constraint Date" attribute is editable only when the value of "Constraint Type" is "Start No Earlier Than" or "Finish No Later Than".
To achieve your requirement, in the editor presentation. you need to use "Timestamp" as the Kind. And in the "Mode" (in the bottom), select "Date".

1 vote

Comments

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,132

Question asked: Apr 29 '14, 9:09 a.m.

Question was seen: 4,621 times

Last updated: Apr 30 '14, 2:53 a.m.

Confirmation Cancel Confirm