How to create a "Requirements Change Request"?
In my Change Management project area I have the "Provides" association of "Requirements Change Request" with the Requirements artifacts container. But neither in the Change Management project area or the Requirements project area I can create a Requirements Change Request.
How can I create a Requirements Change Request?
|
Accepted answer
With the "Requirements Change Request" association, you can create a "Track Requirements" link from the work item in CM.
Frank Schophuizen selected this answer as the correct answer
Comments
Frank Schophuizen
commented Apr 29 '14, 6:40 a.m.
Thanks!
So if I understand correctly, the "provides" association does not define an extra work item type in RTC, it does not define an extra relationship type in RTC, but it does enable links between a work item in RTC and an artifacts in the artifact containers using an existing relationship type (in this case "Track Requirements").
|
One other answer
Hi Frank,
You can add a new type of work item and can customize the same as per your projects need.
Regards:
Ankit
|