Sprint Backlog - Roadmap view does not understand dependency between two tasks
Hello,
In Sprint Plan, We have two change requests. Change Request 1 has two Tasks: 53378 - Task 1 & 53379 - Task 2. In planning, Task 1 depends on Task 2. Still in roadmap view Task 1 is planned first (April 4 - April 7) and Task 2 (Apr 10- Apr 20) is planned after that. This means Roadmap view is not able to understand the dependencies between two tasks and plans in order of ID.
How can I correct the same?
Thanks.
|
Accepted answer
In the workitem https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=299981 comment 2, it mentions:
IBM Rational Product User selected this answer as the correct answer
Comments
IBM Rational Product User
commented Apr 28 '17, 10:46 a.m.
Thanks Lily for your help.
Is there a way we can change scheduler to manual schedule based on start dates and end dates defined in work item? Or how road map view and scheduler is intended to be used in RTC? Because, it is a very common use case of having dependencies between tasks and scheduling work as per dependencies.
Thanks.
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.