Plan view

 Hi,

How Can I define  a sprint plan view that all the next plans that  I will create will be based on this definition so I will not need to edit each time the plan?


0 votes



One answer

Permanent link
You can try the following:

In Eclipse, open the project editor. Go to the Process Configuration tab. Open Project Configuration>Configuration Data>Planning>Plan Views.Select your plan view and press the "Promote" button on the top right. Promote the view.
On the Plan Types node, select the plan you want to add your plan view. Add the plan view and save.

Please note there were limitations on promotion of plan views that were lifted in release 4.0.5. If the promote does not work due to this fact, the solution above does not work.

1 vote

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220

Question asked: Feb 24 '14, 4:33 a.m.

Question was seen: 5,367 times

Last updated: Feb 24 '14, 4:44 a.m.

Confirmation Cancel Confirm