Hi,

I'm trying to understand how the new "Quick Planner" works for Team Area's with a new Timeline (and Iteration).

So I've setup a new timeline and create a backlog Iteration;

When I go to the quick planner and I select the new Team Area and then the new Teams Timeline..

As soon as I do that - the Backlog plan view disappears?

Help please...  so I'm trying to understand how on an RTC Project Area we can have Teams using the new Quick Planner and have their own "Backlog"

Thanks

Matt Muller

One answer



permanent link
Guido Schneider (3.4k1491115) | answered Apr 18 '15, 4:55 a.m.
 Do you have marked your Backlog Iteration of the new timekine as "Backlog Iteration" within Eclipse client?

Unfortunately this cannot be done in web UI. 
There is an enhancement request for this available. Have to search for the ID.

Regards
Guido