RTC Milestones calculated date is incorrect

Hi,
We are using RTC 4.0.1 with "formal template". We are facing a problem when using Milestones.
We are using MS for 2 purposes:
  • Mark the starting point (date) for group of tasks - In this case we set the MS date by using the "start not earlier than" constraints, and set the MS to be the predecessor of the tasks. This works fine.
  • Mark the completion (date) for group of tasks - In this case we define the tasks to be the predecessors of the MS, and let RTC calculate the MS date. In most cases this works fine, and the MS date is the shows the completion date of the last task. However, sometime a delay is shown (as can be seen in the below screenshot). This looks like a bug in RTC

More details:

  • If we change the owner of the MS, then the calculated date is changed.
  • We tried to give the MS higher rank, but this did not solve the problem.
  • We plan to use MS to sync between different parts of the same plan, and also to sync between different teams. Hence Ms are of high importance.




What am I missing?

Thanks,
Raviv.

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jan 24 '14, 4:50 a.m.

Question was seen: 3,832 times

Last updated: Jan 24 '14, 4:52 a.m.

Confirmation Cancel Confirm