How is Release Planning Load calculated at RTC 4.0.5
![]()
Hi,
I want to analyse planning calculation in RTC and hence wish to know how is Release Planning Load calculated at RTC 4.0.5.
Therefore, I defined an iteration in the future with only 3 days duration. In the Project Area are no Team Members defined. Creating a Release Plan with no WorkItems associated shows me a load of 3.25 hrs. After adding a team Member with 5 * 8 hrs working capacity the plan load is calculated to 51.25 hrs.
Can you please explain the calculation concepts used by RTC?
Regards,
Kunal
|
Accepted answer
![]()
The article https://jazz.net/library/article/586 explains the concepts of progress bars and load bars. I tried the scenario mentioned:
- Create a project using the OOTB Scrum template.
- Create an iteration defined in the future with only 3 days duration (please note not just the date but also the time for the iteration start and end date).
- Create a Release plan for the project for the above iteration.
>> When there are no users in the projects the load bar in the release plan shows 0/0
>> When a user with default work environment is added to the project it shows 0/24 as expected.
To answer your question on the parameters that is used to calculate the load bars:
- Iteration start/end dates
- User work environment which includes:
* Work days
* Work allocations
- Scheduled absences during the iteration duration
- Work items estimates/timespent etc
Can you provide more details of the work environment for the user added to the project?
Kunal Doddanavar selected this answer as the correct answer
|
Comments
Hi Kunal,
There will be some user who is currently creating the plan.