How is Release Planning Load calculated at RTC 4.0.5
Hi,
I want to analyse planning calculation in RTC and hence wish to know how is Release Planning Load calculated at RTC 4.0.5.
Therefore, I defined an iteration in the future with only 3 days duration. In the Project Area are no Team Members defined. Creating a Release Plan with no WorkItems associated shows me a load of 3.25 hrs. After adding a team Member with 5 * 8 hrs working capacity the plan load is calculated to 51.25 hrs.
Can you please explain the calculation concepts used by RTC?
Regards,
Kunal
|
Accepted answer
The article https://jazz.net/library/article/586 explains the concepts of progress bars and load bars. I tried the scenario mentioned:
- Create a project using the OOTB Scrum template.
- Create an iteration defined in the future with only 3 days duration (please note not just the date but also the time for the iteration start and end date).
- Create a Release plan for the project for the above iteration.
>> When there are no users in the projects the load bar in the release plan shows 0/0
>> When a user with default work environment is added to the project it shows 0/24 as expected.
To answer your question on the parameters that is used to calculate the load bars:
- Iteration start/end dates
- User work environment which includes:
* Work days
* Work allocations
- Scheduled absences during the iteration duration
- Work items estimates/timespent etc
Can you provide more details of the work environment for the user added to the project?
Kunal Doddanavar selected this answer as the correct answer
|
One other answer
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Hi Kunal,
There will be some user who is currently creating the plan.