RTC Planning capacity

The capacity of a person cannot be altered at the task level. It only allows to be held at the resource level. Is there any work around for this?

0 votes



One answer

Permanent link
RTC Planning is not designed for this kind of micro management. You can only manage the over all allocation of a person and the scheduler takes that into account. Each task is expected to be executed with maximal allocation and once it is finished, the next one is executed.

1 vote

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 239

Question asked: Dec 05 '13, 12:51 a.m.

Question was seen: 7,116 times

Last updated: Dec 05 '13, 7:22 a.m.

Confirmation Cancel Confirm