How to found all task linked to a test case?


Cedric HERRIER (345) | asked Oct 04 '13, 9:08 a.m.
retagged Oct 04 '13, 9:57 a.m. by Tory Jaskoviak (52015)
 Hello

I have lot of task linked to test cases.

One test case can be linked to a lots of task .

I wan to know how can I found all the task linked to a specific test case?


Best regards


One answer



permanent link
Ajay Chebbi (3113) | answered Oct 08 '13, 2:27 a.m.
JAZZ DEVELOPER
edited Oct 08 '13, 2:27 a.m.
@Cedric you can go to a your test case and look under "Development Items" section. If you want to look at all of them then you can go to Browse>Test Cases and switch to the "Traceability view" in the top "View as" drop down.

Comments
Cedric HERRIER commented Oct 08 '13, 2:57 a.m. | edited Oct 09 '13, 3:41 p.m.

 Hello Ajay


Thanks for your answer. I am ok for all test case / test plan but for test suite it doesn' t work. For Test suite the view "Traceability" is not available.

Is it possible to have the same view for the Test Suite?