Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

epic progress/estimate does add up to 100%

I have 1 epic with 2 children stores (8 pts and 13pts) and one story has child task 4 hours.

In plan view, the epci progress says

progress: 0/21pts estimated 75% <- why not 100%?

progress: 0/4hrs estimated: 100% <- OK, appears correct

what's missing?

0 votes

Comments

Do any of the child work items have value in Time Spent ?  I think that will dial back the overall estimates.


Accepted answer

Permanent link
Here is the explanation regarding estimate % :

estimate % is the average of the plan items estimated % and the execution items estimated %

Estimate = ( [% plan items estimated] + [% execution items estimated] ) / 2

With 1 Estimated Story (plan item) and 1 non-estimated task (execution item):
plan items estimated % = 100 (1/1)
execution items estimated % = 50 (1/2) - the denominator here includes the story item as well
average =  (100 + 50 ) / 2 = 75%

The question on why denominator in execution items % calculation is under debate but for now its included.

The top level plan item being considered in estimate calculation is something under discussion or rather a debate.
An enhancement 
193444: Story progress should not include itself
already exists.  Though this is raised for Story work item, it applies to all top level plan items.

I would suggest you review this Enhancement and if you find it relevant, comment and continue discussions directly there.

There is also a forum post on this :
https://jazz.net/forum/questions/104272/percent-estimated-calculation-has-changed-since-upgrade-where-are-settings

Hope this helps!
Ralph Schoon selected this answer as the correct answer

0 votes


One other answer

Permanent link
 Hi Marek Siekierski,

I have tried the above expression to get the estimated value on Epic. But i haven't successful on calculating the estimate in EPIC WI.

Please explain process to calculate estimated value in EPIC workitem using the below use case. 

Use Case:
We have a stories under an epic, story has 5 tasks as a children, all tasks were estimated and has some time spent values as below.

- Epic (Progress - 0/5pts | 10/50hrs    Estimated: 93% )
    - Story 1 (Progress - 0/5pts | 10/50hrs    Estimated: 100% ) and Status: In Progress
          - Task 1 (Status: In Progress,  Estimate - 10 h , time spent - 2 h )
          - Task 2 (Status: In Progress,  Estimate - 10 h , time spent - 2 h )
          - Task 3 (Status: In Progress,  Estimate - 10 h , time spent - 2 h )
          - Task 4 (Status: In Progress,  Estimate - 10 h , time spent - 2 h )
          - Task 5 (Status: In Progress,  Estimate - 10 h , time spent - 2 h )

We can see story has Estimated as 100%, but how EPIC workitem progress bar shows estimated as 93% ?  

Thanks in advance.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,024

Question asked: Sep 12 '13, 11:46 a.m.

Question was seen: 4,617 times

Last updated: Aug 18 '16, 12:53 a.m.

Confirmation Cancel Confirm