Hello,
Is it possible to get historical data in BIRT for the attribute DUE DATE.
I don't see this information  in table WORKITEM_CHNGS stored in the WORKITEMS_SNAPSHOT.
Thanks in advance for your help

1 vote


Accepted answer

Permanent link
Zack, try

Live_Workitem_Cnt  Due_Date field

SG

Zachary K selected this answer as the correct answer

0 votes

Comments

Thanks Sandy

@zachary, I thought you were looking for historical data... To my understanding, this Live_Workitem_Cnt only contains live data. For example, if the due date was changed several times, the due date in the Live_Workitem_Cnt would only show the current.


The historical data are ETLed into those work item changes table when snapshot is running. 

@sandyg, can you confirm? Thanks.

Correct, the table to use is WORKITEM_CHNGS not Live_Workitem_Cnt


One other answer

Permanent link
Did you check WC_TIMESTAMP_EXT? 

Thanks.

0 votes

Comments

Wc_TIMESTAMP_EXT is only for custom attribute.  Duedate is a build-in attribute 

Sorry, you're right 

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 324
× 26

Question asked: Jul 11 '13, 4:21 p.m.

Question was seen: 4,438 times

Last updated: Jul 12 '13, 2:18 p.m.

Confirmation Cancel Confirm