Hi all,

Is there a way that we can map the MSP attributes with the RTC Attributes in Project Plan

For EX: Start date, End Date & predecessors when using Formal Project management process

We are trying to import a MSP plan created in MSP 2010 into RTC 4.0.1
The MSp Plan has attributes like Start date, End Date & predecessors while the same attributes are not available in RTC Formal Project Management process.

When we import the plan the default values in RTC are not filled and having difficulty in manually entering them
for all attributes

Any alternate to achieve this??
Anish

2 answers



permanent link
Millard Ellingsworth (2.5k12431) | answered Jul 15 '13, 7:14 p.m.
FORUM ADMINISTRATOR / JAZZ DEVELOPER
There is a discussion of Microsoft Project and RTC integration, including attribute mapping, here: https://jazz.net/library/article/1150

permanent link
Ken Tessier (84117) | answered Jul 17 '13, 5:34 p.m.
See also Importing and exporting plans in the information center.