How to set the milestone WI date in traditional project?
I use traditional project template, and there is milestone work item type. It shows black point in gantt view. But how can I set the milestone WI date? I want to set some important milestone in my project, but I only see the milestone WI is shown just as its create date.
Thanks!
|
Accepted answer
You can set the constraint date for the milestone. Related article: https://jazz.net/library/article/657/ Jia Jia Li selected this answer as the correct answer
|
Your answer