Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Can I have multi-iteration plans on one iteration plan?

I am able to create two iteration plans from the same iteration for two components. But I found one issue: the work items I added to one plan also show up in the default Defect & Enhancement folder of the other plan. And I can't delete the default Top and Defect & Enhancement folders.

How do I remove work items from one plan, or move them from one plan to another plan? I know I can move them around different folders in the sam plan.

0 votes



One answer

Permanent link
ghu wrote:
I am able to create two iteration plans from the same iteration for
two components. But I found one issue: the work items I added to one
plan also show up in the default Defect & Enhancement folder of
the other plan. And I can't delete the default Top and Defect &
Enhancement folders.

How do I remove work items from one plan, or move them from one plan
to another plan? I know I can move them around different folders in
the sam plan.


This is by design. Understand a plan as a work item query with a rich
presentation. The capture is the selected team area and iteration.
Hence, if you create two plans for the same iteration and team area the
same items will be included, namely those that are planned for the
respective iteration and belong to a category that is associated with
the team area.

--
Cheers, Johannes
Agile Planning Team

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Dec 01 '08, 4:01 p.m.

Question was seen: 7,125 times

Last updated: Dec 01 '08, 4:01 p.m.

Confirmation Cancel Confirm