What is the customer GA date for RTC/CLM 4.0.2?


Angelo Giampa (3188) | asked Feb 21 '13, 12:04 p.m.
I have not been able to find this information on the RTC maintenance dashboard. 
If I query on items planned for iteration 4.0.2 Final, one item shows up, related to Releng testing but no info on release date. So, could you provide a release date for 4.0.2, please? 

One answer



permanent link
Robin Bater (3.4k47) | answered Feb 21 '13, 1:23 p.m.
JAZZ DEVELOPER
Here is a link to the CLM 4.0.2 Plan

https://jazz.net/jazz/web/projects/Jazz%20Collaborative%20ALM#action=com.ibm.team.apt.viewPlan&page=com.ibm.team.apt.web.ui.plannedItems&id=_Al0pgGo_EeKiFIwlI6j0YA&planMode=com.ibm.team.apt.viewmodes.internal.iteration

If you look under the plan details this typically indicates when development is planned to be finished, with actual GA depending upon time needed to release for manufacture time  and configuring on jazz.net.

Comments
Angelo Giampa commented Feb 21 '13, 2:17 p.m. | edited Feb 21 '13, 2:57 p.m.

Thanks Robin! 

Funny thing though - there are no items showing in any of the iterations. Is that normal? Shouldn't I at least see items related to "...manufacture..." and "...configuring on jazz.net." planned for CLM 4.0.2 Final?


Robin Bater commented Feb 21 '13, 5:28 p.m.
JAZZ DEVELOPER

Hi Angelo,

This plan just specifies the high-level iterations, the individual work for each capability like Jazz Foundation, RTC, RRC, and RQM are covered in related individual project plans (where there might be more than one), for example:

The Jazz Collaborative project area dashboard contains links to other dashboards (in the 4.0.2 CLM Dashboards widget) which are on different servers. From those individual dashboards you can see (if authorized) the current plans like the RM V4.0.2 plan which is contained in the RM project area.

Now the plans obviously only give an intended target date and we self-host the milestones as part of the proof but there can always be last minute surprises that adjusts when a release is GA'ed.





Geoffrey Clemm commented Feb 21 '13, 6:06 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

For a better example of a CLM release plan, see the CLM-4.0.3 plan:
https://jazz.net/jazz/web/projects/Jazz%20Collaborative%20ALM#action=com.ibm.team.apt.viewPlan&page=com.ibm.team.apt.web.ui.planlinks&id=_L5YHTT0iEeK0Mewj8hAh8w
In particular, you will see that the CLM plan is explicitly linked to the contributing plans.