This article is a summary of the process used by three different IBM teams to upgrade their CLM systems. Consider this document as a best practice for upgrading CLM from version 4 to another version 4. Times are approximate and do not reflect a supported performance standard by IBM.

The three teams are the following:

  1. The Functional Verification Test Team (FVT) tests the upgrade process before IBM ships the product. They perform upgrades from one Sprint milestone to another Sprint milestone.
  2. The Rational Engineering Service (RES) team manages the self host server, jazz.net, where most CLM developers work. The upgrade occurs every sprint. They manage 30 other CLM systems. In some systems, the upgrade occurs daily, using the latest build.
  3. The Hursley team manages just over one hundred CLM production systems which support development teams including WebSphere, MQ and CICS

In this document, we are listing the set of high level steps each of the previously named teams use. We also give an estimate on how long each task takes.

Preconditions

Before one can upgrade, there must be an environment to upgrade. This article does not explain how to install a new server. The RES/Hursley teams have existing systems in staging and production. To test the upgrade process, FVT first installs an environment on a cloud system.

All three teams based their best practices out of the existing documentation to upgrade a CLM system. We highly suggest you become familiar with such documentation before exploring the best practices. Understand the Upgrade Process (IBM InfoCenter)

Retrieve the installable binaries from the server – 1 hour

The FVT team retrieves the build to download based on the build ID. They download the binaries from an internal site. The Hursley team uses the official external link and downloads the binary on a staging server. They perform 3 manual installations in a local staging server; they install a server in three different context root setup. This step is manual, there is no response file. The RES team downloads the ZIP file for a certain build identifier from an internal website.

Generate a response file – 15 minutes

The FVT team has a GUI application that generates a specific response file. The Hursley Team generates a new migration script for each version. Each script contains the hardcoded location of the local staging server. RES does not use IBM Installation Manager (IIM) and thus does not have a response file. Instead, a set of configurable arguments are stored in a configuration file and referenced by the script.

Lay out files on the file system – 5 minutes

The RES team unzips the zip file in a directory based on BUILD ID. The script uses a configuration file/response file. The FVT team uses IBM install Manager (IIM) and installs the new CLM in a location specified by the user response file. The Hursley script copies files from the local staging server to the instance server using the generated script with hardcoded path. The files are copied to a new location, preserving the files associated with the original CLM release in case the upgrade needs to be backed out.

Massaging extracted files – 5 minutes

The FVT team does not modify any files. The Hursley team runs a script to combine the configuration files, modify the tomcat LDAP realm, and change some log properties. They created this script. The RES team uses a script to setup the context root links, rename the WAR files, and create links for the renamed WAR files. This is done to easily track which specific build/version is deployed on which application server in WebSphere at a glance. They also open and update the WAR files with a custom theme and modify the default authentication method. They also created the script themselves.

Pre-upgrade before outage – 5 minutes

This step is to prepare the migration process as much as possible without starting any server outage to the current production system. The RES team runs their CLMTOOLS script, that mimics the upgrade wrapper migration part of the script but does not run any addTables script. They also validate the online backup of the database is running.

Outage – start – 5 minutes

At this point, each team stops the Application server to be upgraded.

Backup – 10 minutes

After the server is down, the HURSLEY and RES team do a validation of the incremental online backup and then execute the indexes backup. For the RES team, the index backup is a disk copy of indices to a different location. For the Hursley team, the index backup is a filesystem backup to Tivoli Storage Manager.

Upgrade - 25 minutes

The FVT team runs the upgrade wrapper script. This performs all the tasks in silent mode: Migrate, re-index (if required) and addTables. The Hursley team changes the database userid permissions to allow changes to the structure of the database, which is not permitted under day-to-day conditions, and then runs the update wrapper script to migrate the server. The RES team executes the install and addTable part of their CLMTOOLS script. This runs a script to remove old War files and install news ones, and then executes all addTables.

Post upgrade cleanup – 5 minutes

Hursley runs a script to cleanup their tomcat work directory. RES also runs a script to clean up all temporary directories for WebSphere.

Outage – stop – 10 minutes

At this point, the Hursley team copies the upgrade logs and application server logs to a safe place. They clean all system logs and start the Application server.

Manual steps to finalize upgrade – 20 minutes

All teams manually migrate Requirement Manager (RM) application. If needed, they manually install the licenses and do a quick validation of the system.

Related topics: Deployment web home, Installing, upgrading and migrating

External links:

  • None

Additional contributors: None

Edit | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r10 < r9 < r8 < r7 < r6 | More topic actions
 
This site is powered by the TWiki collaboration platformCopyright © by IBM and non-IBM contributing authors. All material on this collaboration platform is the property of the contributing authors.
Contributions are governed by our Terms of Use. Please read the following disclaimer.
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.