Can I control the order of things in the Planned For field?


Bharath Adhithya (5213352) | asked Nov 01 '12, 12:40 a.m.
edited Nov 01 '12, 1:03 a.m. by David Olsen (5237)
Hi,

Is it possible to have the release months in the planned for field in an non-alphabetised order?

Thanks,
Adhithya

One answer



permanent link
Lauren Hayward Schaefer (3.3k11727) | answered Nov 01 '12, 6:57 a.m.
JAZZ DEVELOPER
I don't think it's possible to sort the items in the planned for field.  I found another post that suggests naming the iterations using numbers so they will be in the correct order:  https://jazz.net/forum/questions/92768/planned-for-iteration-displays-in-alphabetical-order.

If this feature is important to you, you can submit an enhancement request.