How to view burndown chart for completed sprints?
Hi, I have recently started using RTC for my project. I couldn't find any option to view burndown chart for completed sprints. Someone please help. Pramod |
Accepted answer
Hi Pramod,
You can view the release burndown on your dashboard. Go to your dashboard. Click Add Widget. In the Select Catalog dropdown box, be sure your change and configuration management project is selected. Find the Release Burndown widget and click Add Widget. You can configure the widget's query to include whatever iterations you'd like. Pramod Kumar D selected this answer as the correct answer
|