Unable to duplicate a plan


Feng Liu (511125) | asked Sep 22 '08, 5:39 a.m.
I'm trying to duplicate a plan from the Project A to the Project B which are created using the same process template. But there are two problems I've encountered.

One is for duplicating a simple plan. After duplicating that, I got an empty copied plan which haven't any work items within it.

Another case is for duplicating a complex plan which created by other team member. When I try to duplicate it, an exception is thrown which is shown as below:
Problem
An error occurred during "Save Iteration Plan".

CRJAZ0215I Item not found: com.ibm.team.process.internal.common.impl.TeamAreaHandleImpl@77367736 (stateId: , itemId: , origin: <unset>, immutable: <unset>)

So, how can I duplicate a plan from one project to another project? Is this possible in current release of the RTC?

Many thanks in advance.

One answer



permanent link
Johannes Rieken (1.2k1) | answered Sep 23 '08, 3:43 a.m.
Hi there

One is for duplicating a simple plan. After duplicating that, I got an
empty copied plan which haven't any work items within it.

That is correct. Duplicating a plan does not include work items. Think

of a plan as a special query and query result presentation.



CRJAZ0215I Item not found:
com.ibm.team.process.internal.common.impl.TeamAreaHandleImpl@77367736
(stateId: , itemId: , origin: <unset>, immutable:
unset>)

So, how can I duplicate a plan from one project to another project? Is
this possible in current release of the RTC?

Are both projects in the same repository? Please file a bug with the
full stacktrace.

--
Cheers, Johannes
Agile Planning Team