How to change default Work Item type for Implemented By Link?


Timur Markunin (6495166146) | asked Jul 25 '12, 4:35 a.m.
Hello,

I'm trying to customize Formal Project Management RTC template. As a part of the customization I want to change default work item type for Implemented By link from Change Request work item type to Task work item type.

How could I achieve this goal?

-Thanks in advance

One answer



permanent link
Timur Markunin (6495166146) | answered Jul 25 '12, 5:10 a.m.
I've found the answer:

I need to open Project Area Template and change  Change Management Type Binding for Implementation Request from Change Request to Task