How to estimate how long it will take to automate tests?
I have been asked for metrics, figures etc on how long it takes to automate tests and how to evaluate the test automation effort. I know, I know. A piece of string is LONG. How long???
I am more looking for documents that help estimate based on previous experience, complexity, preparedness. GATNER reports etc would be great too. I am interested in Functional Tests at the moment but have offered a performance example below.
I have a fair bit of automation experience and know it is hard to provide concrete estimates. I am starting out from scratch with RFT and have not used it in the past so there is a learning curve.
When asked I provided an example from the past. I attempted to automated 13 load / stress tests within 2 months. Managed to get 11 running reliably, providing readable results / metrics and complete reuseability through data driven testing. I know is sounds like a long time, but previously it had taken 3 guys a month to do the same tests using a different product. This I felt was a starting bench mark, but not functional automation testing. |
One answer
I think the question you asked is more relevant to the 'probationer' to answer it.
|