From which ODS table in RRDI 2.0 ( with CLM4.0) , I can get Proposed Start Date , Proposed End Date , Planned Start Date , Planned End Date
PRASANTA CHAUDHURI (110●3●20●25)
| asked Jul 10 '12, 11:57 a.m.
retagged Jun 14 '13, 1:38 p.m. by Michael Prentice (62●2●9●13)
RRDI 2.0 has been installed and integrated with CLM 4.0 . I have used Formal Process in RTC . Taken Proposed Snapshot with estimates for a setsof workitems. Modified estimates for few workitems then taken Planned snapshots . My question how and from which ODS table in RRDI 2,0 , I can get Proposed Start Date , Proposed End Date , Planned Start Date , Planned End Date fields .
Thanks & Regards PKC |
2 answers
Hello
try these data dictionaries available in the infocenter: http://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m3/topic/com.ibm.team.reports.doc/topics/ccm-roles.html And this is what is populated in the FM model by CLM apps: http://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m3/topic/com.ibm.rational.reporting.overview.doc/topics/c_reference_datadictionary_clmmetrics.html |
Hi PKC,
I believe those dates are not visible outside of plans so not pushed to the DW as they are calculated internal values for the plan snapshots. Having said that I don't know if you have seen the GADO Focal Point-CLM integration? This uses an internal service to pull a couple of details from a plan snapshot. It doesn't go into the DW but is one way to at least get to them. |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.