Wrong Dates in Iteration Plan

I have an iteration set in Process Iterations to begin on 8/15 and end on 9/12. But on one person's screen it shows up as 8/14 to 9/11, it seems to be fine for other people. Any idea what could be causing this?

0 votes



3 answers

Permanent link
Are there time zone differences between the server and the person's
machine?

Kai
Jazz Process team

icewsu2002 wrote:
I have an iteration set in Process Iterations to begin on 8/15 and end
on 9/12. But on one person's screen it shows up as 8/14 to 9/11, it
seems to be fine for other people. Any idea what could be causing
this?

0 votes


Permanent link
Yes, the server is on eastern time and the client is on mountain time.

0 votes


Permanent link
is there a workaround?

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Aug 18 '08, 4:06 p.m.

Question was seen: 7,525 times

Last updated: Aug 18 '08, 4:06 p.m.

Confirmation Cancel Confirm