Is there a way to define a query that finds work items with no due date specified? I seem to only be able to provide conditions that would apply if a due date was supplied.

0 votes



3 answers

Permanent link
Is there a way to define a query that finds work items with no due
date specified? I seem to only be able to provide conditions that
would apply if a due date was supplied.

you can add a "Due Date" condition and check the "Unassigned" checkbox.

--
MikeS
Jazz Agile Planning team

0 votes


Permanent link
You can do so in the RCP UI, but not in the Web UI yet. I've opened work item 59775 to track this.

Christof
Jazz Work Item team


marenn wrote:
Is there a way to define a query that finds work items with no due
date specified? I seem to only be able to provide conditions that
would apply if a due date was supplied.

0 votes


Permanent link
Ah... you are correct. I am trying to do this in the Web UI... doing it in the RCP UI doesn't solve my need. Thank you for opening a work item.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Aug 11 '08, 8:48 p.m.

Question was seen: 6,074 times

Last updated: Aug 11 '08, 8:48 p.m.

Confirmation Cancel Confirm