Hello All,

In Project Area Initialization we can create server follow-up action
so i can create Team Area and Workitem Categories there ,

We want to Create associated team area with categories in Project Area in Project Area initialization.

is this possible ?

-Thanks
Teguh

Accepted answer


permanent link
Geoffrey Clemm (30.1k33035) | answered Jul 31 '13, 11:21 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

In RTC-4.0.3, there is a Create_Team_Areas server follow-up action you can select to automatically create a set of team areas.

teguh fihaiman selected this answer as the correct answer

One other answer



permanent link
Thomas Yu (45183) | answered Aug 01 '13, 6:38 a.m.
edited Aug 01 '13, 6:40 a.m.
You can create Team Areas in the project area initialization follow up action, but you can NOT configure work item category associated with team areas.