Delivery permission
![]()
In RTC either developer can be granted deliver permission or cannot be granted delivery permission.
Is there any option where the delivery to the developer can be granted on approval ? or this has to be taken care in the Task workflow state and preconditions ? i.e the developer can deliver the task only if the task is in approved state ? if this is the only way how to make this change ? -Thanks Ban |
3 answers
![]()
Geoffrey Clemm (30.1k●3●30●35)
| answered Apr 04 '12, 12:24 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Requiring the appropriate approvals in the task is the only way I know to do it (other than writing your own custom process pre-condition). Is there a reason why you don't want to use task approvals ?
Cheers, Geoff In RTC either developer can be granted deliver permission or cannot be granted delivery permission. |
![]()
Hi Geoff,
how to set this up ? like devl cannot deliver the task to the stream unless approved by the team lead. Do you have steps/documents i can follow -Thanks |
![]()
Ralph Schoon (63.3k●3●36●46)
| answered Apr 05 '12, 7:02 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER Hi Geoff, Have a look into the help here: http://publib.boulder.ibm.com/infocenter/clmhelp/v3r0m1/topic/com.ibm.team.platform.doc/topics/t_projects_teams_process.html Here is another source: https://jazz.net/library/article/137 search for precondition. |