what are the practices for users that want to wait for team member deliveries to be qualified before accepting them?

One answer



permanent link
Geoffrey Clemm (30.1k33035) | answered Mar 10 '12, 3:27 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Create a "qualified stream" to contain the qualified deliveries.
Deliver changes to that stream only when they have been qualified. Then
users that only want to accept qualified changes would select the
"qualified stream" as the current flow target of their workspaces.

Cheers,
Geoff

On 3/10/2012 7:41 AM, jennieabrown wrote:
what are the practices for users that want to wait for team member
deliveries to be qualified before accepting them?