Unable to create Reports TP- TC when using RRC
I'm using RQM 3.0.1.1 and I'm trying to implement this scenario:
Create Requirement via RQM
Create a Collection Link
Associate Collection link to Test Plan
Associate single requirement of collection to Test Case
Now I want thjs report:
Plan requirement Coverage detail
Plan Requirement coverage by Test Case
But report display nothing
I also try run DataWarehouse job (an all project associate), but the result was the same.
How I can do it?
Ciao
Create Requirement via RQM
Create a Collection Link
Associate Collection link to Test Plan
Associate single requirement of collection to Test Case
Now I want thjs report:
Plan requirement Coverage detail
Plan Requirement coverage by Test Case
But report display nothing
I also try run DataWarehouse job (an all project associate), but the result was the same.
How I can do it?
Ciao
3 answers
Typically you would only run them once a day, but theoretically you can
run them more often by changing the interval in the jts/admin >
Reporting page. Check how long jobs took in the past and schedule enough
buffer time so that they would not overlap. Note, that if there are a
lot of changes in a day the jobs can take longer.
Peter.
On 1/24/2012 5:53 AM, oreste wrote:
run them more often by changing the interval in the jts/admin >
Reporting page. Check how long jobs took in the past and schedule enough
buffer time so that they would not overlap. Note, that if there are a
lot of changes in a day the jobs can take longer.
Peter.
On 1/24/2012 5:53 AM, oreste wrote:
I solved the problem runnin the "data warehouse collection
jobs".
Can I change this job every 15 minutes?
Ciao