Doubts with Execution trend report
I am currently facing a problem with Execution trend report. Irrespective of Execution record update, I'm not getting the "completion" data updated in charts.
Steps
--------
1. created a test plan
2. added 1 schedule / milestone with planned and actual dates
3. generated points projection (75 points) (on a daily basis) for 5 days
4. created execution records and updated it regularly.
5. We do not have any automation with rqm. hence, while updating the execution result, i choose "Create result without execution" and select "passed". this was done on every day..
6. Checked that the background data collection job runs every night. the other report "Execution and defects" (which reads from DW) was showing the updated data. However, this is done by our IS Team.
7. But, the execution trend report still shows only 4 points as completed. Though the points updated is around 32 points and attempted is around 43.
Can anyone tell me where I would have missed something?
RQM Version - V3.0.1
Steps
--------
1. created a test plan
2. added 1 schedule / milestone with planned and actual dates
3. generated points projection (75 points) (on a daily basis) for 5 days
4. created execution records and updated it regularly.
5. We do not have any automation with rqm. hence, while updating the execution result, i choose "Create result without execution" and select "passed". this was done on every day..
6. Checked that the background data collection job runs every night. the other report "Execution and defects" (which reads from DW) was showing the updated data. However, this is done by our IS Team.
7. But, the execution trend report still shows only 4 points as completed. Though the points updated is around 32 points and attempted is around 43.
Can anyone tell me where I would have missed something?
RQM Version - V3.0.1