It's all about the answers!

Ask a question

Querying across project areas


Matthew Bradley (1133) | asked Nov 29 '11, 5:38 a.m.
Is it possible to query across all or multiple project areas in RTC? On the "Details" tab in the query editor I see "Team and Project Area" sharing but I only see the current project area in there and no others.

Does anyone know if there is something similar in RQM and RRC, allowing queries across all or multiple project areas?

Thanks!

6 answers



permanent link
Steven Jin (10697) | answered Nov 29 '11, 9:51 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
This cannot be done with the current release of RTC.

There is a work item for it:
"Support work item queries across project areas"
https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=94575

permanent link
Matthew Bradley (1133) | answered Nov 29 '11, 1:00 p.m.
Thanks for your reply stevenyj!

Does anyone have any ideas on whether this can be done for RQM or RRC?

Thanks.

permanent link
Geoffrey Clemm (30.1k33035) | answered Nov 30 '11, 11:38 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
To my knowledge, none of the Jazz products officially support querying
across project areas. What is officially supported is reporting across
project areas.

Cheers,
Geoff

On 11/29/2011 1:08 PM, mattbradley wrote:
Thanks for your reply stevenyj!

Does anyone have any ideas on whether this can be done for RQM or
RRC?

Thanks.

permanent link
Milan Krivic (98010172139) | answered Dec 01 '11, 3:29 a.m.
To my knowledge, none of the Jazz products officially support querying
across project areas. What is officially supported is reporting across
project areas.

Cheers,
Geoff

On 11/29/2011 1:08 PM, mattbradley wrote:
Thanks for your reply stevenyj!

Does anyone have any ideas on whether this can be done for RQM or
RRC?

Thanks.



Yes, Geoff is right. You can create a report for getting work items across the project areas very simply.

Let me know if you need any help with this,

Regards,

permanent link
Gabriela Bernal (011) | answered Mar 19 '14, 2:49 p.m.
 Hi - Know this was posted awhile back - but did anyone find a way to create work item queries across different Projects?

Thanks,
Gaby

Comments
sam detweiler commented Mar 19 '14, 4:25 p.m.

queries are not supported across projects.. they are single project only..


reports support cross project collections 


permanent link
vikrant kamble (1322996) | answered Feb 04 '16, 12:08 a.m.
 Hi All,

Is it supported in latest version of RTC?,
I am using RTC 5.0.2 and it is not supported in 5.0.2, but I don,t know about latest version of RTC.


Comments
Don Yang commented Feb 04 '16, 1:15 a.m.

there is new stuff in v6.0.1 to support workitem filtering across project areas, see details:
https://jazz.net/downloads/rational-team-concert/releases/6.0.1?p=news#crossprojectviews

Your answer


Register or to post your answer.