How to delete Work Item from plan?


Sergey Fayman (122) | asked Jul 10 '08, 8:13 a.m.
Any ideas?

2 answers



permanent link
Elisabeth Carbone (616108) | answered Jul 10 '08, 9:05 a.m.
JAZZ DEVELOPER
Select the WI you would like to remove and on the context menu change the "Plan for" to either another Iteration or "No target Iteration"
Save the Iteration Plan.

Elisabeth

permanent link
Johannes Rieken (1.2k1) | answered Jul 12 '08, 10:34 a.m.
Technically, an iteration plan is just a work item query, e.g. all work
items that are planned for a certain iteration and are associated with a
selected team area. So, if you want to 'delete' an item from a plan,
you have to modify it so that it does not match the plan query anymore.


--
Cheers, Johannes