Hello Experts,

Currently I am using RTC 3.0.1. I want to link Two different Work Item types.
The Scenario is as follows:

When I complete the Transitions of one WorkItem Type, for example Task, at the end of the transition it should be linked to another work Item type say Defect.

How can I create the same scenario in RTC....

Thanks
Shruti Joshi

One answer



permanent link
Ralph Schoon (63.1k33646) | answered Aug 29 '11, 8:51 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi,

in general there is a link tab, where you can link work items together. Just go there, pick the link type, pick the end point and save.

If you are asking, how you can make sure that relationship of a specific kind is there, I think you would have to create a process advisor/precondition that makes sure it is there. The Extensions Workshop shows how that is done in general: https://jazz.net/library/article/634 .