Can I use RTC milestones in RQM?

I'm looking at lining up the defined milestones in RTC in our RQM projects. We have been doing this manually in v2.x. Is there a way to link the milestone definitions (name and dates) in RTC to the test milestones in RQM? This would help us to stay in synch. It also (hopefully) helps in reporting work in both RTC and RQM per team.

We are looking to move both products to v3 this year.

rns

0 votes



One answer

Permanent link
Hi Robert
You can not use RTC milestone in RQM, however from v4.0 RQM also supports creating timelines and iteration in a similar fashion like RTC. These timelines are defined for project area and can be shared among all test plans within it. See What is new in RQM 4.0

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Apr 05 '11, 11:26 a.m.

Question was seen: 4,553 times

Last updated: Jun 20 '12, 2:34 a.m.

Confirmation Cancel Confirm