Plan - Problem to show progress information

I'm evaluating a scenario with defect work item type as top-level and tasks as execution items.

After simulate some defects and tasks, when I create a plan, defect's inline progress information isn't displayed when the're some children tasks with estimate and time spent values. The characters "--" keeps displayed.

P.S.: The group's ou plan's progress bar is displayed correctly. In addition, when progress bar is added to defect presentation, this information is displyed correctly too.

Any idea what is going wrong?

Tks in advance.

Adriano Farias.

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Mar 30 '11, 4:10 p.m.

Question was seen: 3,161 times

Last updated: Mar 30 '11, 4:10 p.m.

Confirmation Cancel Confirm