Estimated Build completion time not showing.

Hi,
I have observed that,the first build from a newly created RTC build defintion does not show the estimated build completion time. This behaviour is observed in the eclipse client for RTC.

Please confirm if this an expected behaviour.


Regards
Sanfi

0 votes



2 answers

Permanent link
Hi,
I have observed that,the first build from a newly created RTC build defintion does not show the estimated build completion time. This behaviour is observed in the eclipse client for RTC.

Please confirm if this an expected behaviour.


Regards
Sanfi


Hi Sanfi,

This is the expected behavior. The estimated completion time is based off an average and since it is the first build, there isn't anything to calculate the average yet.

Brent Ulbricht
Developer/Lead - RTC Build

0 votes


Permanent link
Hi Brent,
Thank you for the prompt reply.

Regards
Sanfi

Hi,
I have observed that,the first build from a newly created RTC build defintion does not show the estimated build completion time. This behaviour is observed in the eclipse client for RTC.

Please confirm if this an expected behaviour.


Regards
Sanfi


Hi Sanfi,

This is the expected behavior. The estimated completion time is based off an average and since it is the first build, there isn't anything to calculate the average yet.

Brent Ulbricht
Developer/Lead - RTC Build

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Mar 17 '11, 11:27 a.m.

Question was seen: 6,131 times

Last updated: Mar 17 '11, 11:27 a.m.

Confirmation Cancel Confirm