Suitable types for MS Project plan import
![](http://jazz.net/_images/myphoto/cd0bad765faf5c43a42d2dc5dd95c735.jpg)
Just today I tried to import a MS Project plan into an RTC plan and found that dependencies to other tasks were importet.
Unfortunately dependencies to summary tasks in the MS Project plan seemed to get lost during import because I chose "Change Request" as the type for the summary tasks.
In a second try I tried "Task" for both tasks and summary tasks and it worked.
Which kind of tasks are suitable for MS Project plan import?
How can I find out?
Unfortunately dependencies to summary tasks in the MS Project plan seemed to get lost during import because I chose "Change Request" as the type for the summary tasks.
In a second try I tried "Task" for both tasks and summary tasks and it worked.
Which kind of tasks are suitable for MS Project plan import?
How can I find out?