HI

i have created stories, epics and tasks for an iteration with epic being top level work item, some of the work items have deferred and some are completed. How can i include or move the deferred work items in my next iteration.
since if a story is assigned a new planned for than it wont be counted for the previous iteration.
Can any body suggest what actions are to be used for this, so that the work items be counted in both the iterations

Thanks in advance

0 votes



3 answers

Permanent link
In a sprint/iteration plan in Eclipse, you can right click on a work
item and select the "Continue Work in" operation.

Or you can do it manually, by creating a "related" work item, assigned
to the appropriate iteration. You would then adjust the estimate of the
original work item, to reflect the amount of effort applied to that work
item in the current iteration.

Cheers,
Geoff

On 7/1/2010 5:23 AM, preetskuul wrote:
HI

i have created stories, epics and tasks for an iteration with epic
being top level work item, some of the work items have deferred and
some are completed. How can i include or move the deferred work items
in my next iteration.
since if a story is assigned a new planned for than it wont be
counted for the previous iteration.
Can any body suggest what actions are to be used for this, so that the
work items be counted in both the iterations

Thanks in advance

0 votes


Permanent link
Thanks for the response Geoff.
I selected one of the defect in plans and right clicked . I got the option of continue work in but the sub menu is not displaying. any suggestion

0 votes


Permanent link
It is my understanding that the sub-menu is populated by the iterations
that follow the current iteration. So if there aren't any, create one,
and try again. If there are iterations that follow the current one,
you'll probably need to engage with support, or submit a defect on
jazz.net (unless someone else in the forum has another idea).

Cheers,
Geoff

On 7/1/2010 10:53 AM, preetskuul wrote:
Thanks for the response Geoff.
I selected one of the defect in plans and right clicked . I got the
option of continue work in but the sub menu is not displaying. any
suggestion

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jul 01 '10, 5:20 a.m.

Question was seen: 6,819 times

Last updated: Jul 01 '10, 5:20 a.m.

Confirmation Cancel Confirm