Limiting Current Iteration results to one timeline
![]()
Ali Amini (1●2●1)
| asked Nov 23 '09, 12:49 p.m.
edited Jan 23 '13, 2:55 p.m. by Ralph Schoon (62.0k●3●36●43)
In my project we have multiple timelines. Each for different deliverables each managed by different project mngrs. When I am creating queries (such as impediments) and selecting "Current Iteration" checkbox, I want the results to be limited to only one timeline. Currently it returns current iteration for all the timelines.
Alternatively I can select current iteration at each iteration. But I can not benefit from "Current Iteration" checkbox. I have similar problem with reports such as Burndown. What do you suggest? Ali Amini . IBM WebSphere Commerce |
2 answers
![]()
I'm interested in knowing the answer to this question too.
When we have more than one active timeline (say one for development, another for maintenance), is it really necessary to explicity specify the iteration and team for each report we want to display on a dashboard, and to update each set of report parameters by moving the iteration along as the release progresses? For some reason we can't figure out how to differentiate between one timeline's results and the other's. The results for all active timelines seem to be combined when we select "Current Iteration" for what to display, even when we choose only one timeline. Paul Sims, Agile Development Coach IBM WebSphere Commerce |