It's all about the answers!

Ask a question

RQM: Linking one child test plan to multiple master test plan


Sunil Kumar (27111) | asked Jun 08 '20, 2:54 a.m.
Hello,

I have a question concerning an RQM limitation that we are observing.
We are using test plans and master test plans to structure our test cases.
There is a limitation that a test plan can only be assigned as a child to one master test plan. We would need to assign it to more than one master test plan.
Is this something that can be changed by configuration or is this a tool limitation?

Thank a lot for your suggestion and support.

Regards,
Sunil

Accepted answer


permanent link
Krupa Gunhalkar (4512) | answered Jun 15 '20, 1:38 a.m.
JAZZ DEVELOPER

 Hi Sunil,

Technically its not possible. Ideally One test plan can have multiple child plans, however cannot have multiple Parent Test Plans.

Hope this helps,
Krupa Gunhalkar

Ralph Schoon selected this answer as the correct answer

Comments
Ralph Schoon commented Feb 03 '23, 5:16 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

Parent child relationships are usually implemented as 0..1 to n. 

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.