Is it possible to reference more than one RTC plan, either by querying within RTC or reporting from JRS?
Hello,
Currently using CLM Suite 6.0.6.
I am investigating the use of plans in RTC. I'm curious if there's some way to reference multiple plans, I'd effectively like to create a breakdown of multiple plans and the items they consist of. I can't find an endpoint within the application that allows for referencing plans and I don't see a means to select the plans as artifacts to report on in JRS. Is this possible?
Accepted answer
Timothy,
for all I know, you can not report on one plan let alone multiple. Plans are basically queries on work items that compute some data and display that. The only thing you can report on are the work items.
A plan shows data from a specific scope. One part of the scope is defined by the owner. The plan show work items filed against the owning process area and nested process areas.
The second part of the scope is the iteration. The plan shows work items planned for the iteration and all sub iterations of that iteration.