How to get RTC workitem status history in each Release plan
Hoang Nguyen (11●1)
| asked Sep 16 '19, 10:27 p.m.
edited Sep 17 '19, 1:27 a.m. by Ralph Schoon (63.1k●3●36●46)
Hi,
Is there any way to get RTC work item status list history in releases. For example:
Workitem 1 : Planned for release 1 , which is in a state of Inprogress.
Now same workitem i moved to release 2 , which stateĀ will change to underreview.
So now if i want to see the status of workitem 1 , in both releases together ,any option is there? |
One answer
Ralph Schoon (63.1k●3●36●46)
| answered Sep 17 '19, 6:02 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER Changing the planned for does not change the workflow state. So by changing the "Planned For" attribute no state change to "under review" should be performed.
A Plan in RTC is a view on the work items. The Plans show items organized by iteration (hierarchy) and owner (team hierarchy). As far as I know any item is only showing up in one iteration in the plan, because it can only be in one iteration at the current time.
|