Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Is this report out-of-box?

I want to get a report such that

In the x-axis there should be iterations
In the y-axis total number of work items and total story points in that iteration (both completed and commited)

I mean, we need a trend report for iterations.
Does RTC have such this report? If not, how do I get this presentation.

Thanks.

0 votes



3 answers

Permanent link
Hi Murat, The out of the box Team Velocity and Advanced Team Velocity reports will give you such report but only on story points and story work items.
We do not have such report for counting work items. Feel free to file an RFE and we will consider it for future releases.

1 vote


Permanent link
Murat: For your reference, here is the list of out-of-the-box reports: Change and configuration management predefined reports descriptions

Jenn

0 votes


Permanent link
 Murat my recommendation is to use RRDI 5.0.1. in that way you could develop any report that you want, and this tool is included if you have any jazz product. 

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,381
× 1,220
× 50

Question asked: Oct 17 '14, 4:52 a.m.

Question was seen: 4,940 times

Last updated: Oct 17 '14, 12:30 p.m.

Confirmation Cancel Confirm